Alice Springs : Smith Street Land Development

Australian Property Projects

Land development to a section of land. Included the excavation of buried concrete rubble within the Alice Springs Town Council road reserve. Excavation included the excavation to approx 7.0m deep and removal of concrete, excavation of and burial of concrete within the land development and backfill with clean material within the road reserve. Impact rolling of the site and final grade and levelling.


Approach: 


The project included:


Excavation to approximately 7.0m deep and the removal of concrete

Excavation of and burial of concrete within the land development

Backfill with clean material within the road reserve

Impact rolling of the site and final grade and levelling


Results: Collaboration and innovative thinking meant we completed the project on time and to budget